What’s left?

If we have spent ten years doing this, what exactly are we still paying for?

A restoration program is not one construction job. It is a portfolio of wastewater, septic, stormwater, muck and habitat projects that move through different stages on different timelines.

Current pipeline

232 of 403 projects are complete or in progress.

140 complete92 in progress171 outside those two statuses

The County’s “in progress” category can include design, contracts and active construction. This count is an administrative snapshot, not a measure of ecological completion.

Open the current County status table ↗

The unfinished work

Five plain-language categories.

Septic & sewer

Homes and neighborhoods still requiring connection, replacement or advanced treatment so nitrogen does not keep reaching groundwater and the lagoon.

See septic and sewer projects ↗

Stormwater

Pollution still entering through runoff, canals and drainage systems during ordinary rain and major storms.

See stormwater projects ↗

Legacy muck

Nutrient-rich material accumulated over decades can continue recycling nitrogen and phosphorus internally even after outside sources are reduced.

See the muck evidence ↗

Habitat

Oyster, shoreline and seagrass restoration supports recovery after pollution sources are reduced. Habitat work cannot substitute for source reduction; it complements it.

Find habitat projects ↗

Why continuity matters

Infrastructure takes years before the final invoice is paid.

PlanEngineerPermitBidBuildVerify

A project can be real, funded and moving while expenditures lag. Renewal affects the continuity of the dedicated revenue stream; it does not erase the need for procurement discipline, audit, public oversight or performance verification.

Find your part of the plan

What is being built near me?

Use the project map to filter by place, category and status. Each indexed project links back to public records.