What did we get?
Your ten-year lagoon report card.
Big numbers first. Definitions, caveats and source records are one click deeper. Delivery counts come from the County’s October 2026 progress report; the plan-status snapshot is dated July 24, 2026; money and modeled nutrient figures are dated August 17, 2026.
Work delivered · County October 2026 progress report
Three separate measures. They describe different work and are not added together. See the October delivery record ↗
142Completed community projectsAdministrative · October 2026 report (posted for the October 16 meeting)
2,808Completed homeowner projectsAdministrative · counted separately from community projects
1,094Completed conversions to sewerAdministrative · not added to the other counts
Historical plan-status snapshot · July 24, 2026 County dashboard
The plan has evolved over time; this is not the original 2016 project count or a statement that all 403 were scheduled for completion by 2026. The October 2026 report does not provide a synchronized full project-status register, so this snapshot is retained as dated history and no new remainder is calculated from it.
403Projects in the adopted planAdministrative · July 24, 2026 snapshot
140Completed (July 24 snapshot)Historical · do not compare with the October count above
92In progress (July 24 snapshot)Design, contract or construction
171Not yet complete or in progressArithmetic: 403 − 232 within the July 24 snapshot; not a County status label
Money and modeled benefits · August 17, 2026 dashboard
Revenue collected, actual expenditures, funding associated with projects in progress, outside grants and modeled environmental benefits are different categories. They are not combined, and no arithmetic residual is shown as available cash. The latest quarterly financial tables listed by the County are dated August 21, 2026; they are not October figures.
$539.7MDedicated half-cent sales tax collectedRevenue · County total · August 17, 2026
$119.8MActual expenditures to dateAcross all projects, not only completed work · corroborated by the August 21, 2026 tables
$335.2MFunding associated with projects in progressCounty category · separate from money already spent
$127.3MOutside grants leveragedMoney added beyond the local sales tax
186,885Pounds of total nitrogen kept out each yearModeled estimate from completed projects · August 17, 2026
415,803Additional pounds of total nitrogen per yearModeled estimate when projects in progress are completed
ImprovingBut not recoveredMeasured recovery is real, uneven and reversible
So what remains unfinished?
In the July 24, 2026 plan-status snapshot, 171 projects in the adopted plan were outside the completed and in-progress categories and another 92 were in design, under contract or under construction. The County’s October 2026 report adds newer delivery counts but not a synchronized status register, so these snapshot figures are dated rather than updated. The renewal question is not whether to begin a new restoration program. It is whether Brevard continues the existing effort long enough to finish it.